|  When
the last aircraft has touched down and air traffic is banned until
the next morning, lights go out at Frankfurt/Main International
Airport. Not so, however, for the Northern runway, where hundreds
of floodlights illuminate the area. Dozens of specialized workers
appear at the check-in. After passing through security they head
straight for the runway – they are here to work. Nobody is
late when the shift starts at 10:30 at night, for time is pressing.
Before the runway will be handed back to air traffic at 6:00 in
the morning, the men must have shattered and removed 15 x 60 metres
of runway, built a new base and paved new wearing course. They have
nerves of iron, as it seems. This is the first job site of this
kind in the world. It does not permit delays or downtime.
“This project is a challenge
to everyone – to the workers and to us as manufacturer of
the pavers and provider of services” says Dieter Schwenninger,
applications expert from VÖGELE. He has been part of the team
from the very beginning in order to accurately prepare the SUPER
1900 and SUPER 2100 pavers for their job and to advise the contractor
on all technical issues. The contract for pavement rehabilitation
was awarded to Kirchhoff-Heine Strassenbau GmbH & Co.KG based
at Langenargen, Germany. No more than 9 firms had followed the invitation
to tender by Fraport AG, the airport company, and submitted their
bids, a circumstance not surprising in view of the complexity of
the job.
“We reckon in minutes,
not in hours”
Few contractors are experienced in such projects and risks
are high. “Logistics are of utmost importance,” says
Volker Zintel of Fraport AG. “We reckon in minutes, not in
hours.” That is why Fraport AG spent a whole year preparing
for the project. By summer 2005, rehabilitation of the runway will
be completed after 296 overnight closures. The contract is worth
38M Euros.
For each construction machine
a stand-by unit is available at all times to be on the safe side.
Breakdowns or repairs on site would make it impossible to keep to
the tight work schedule. For every machine its specific position
is defined and for every worker his specific job. From the VÖGELE
range of products, SUPER 1900 and SUPER 2100 pavers with HPC screeds
in TP2 version had been chosen to do the paving job. VÖGELE
engineers and the specialized workers on site prepared the pavers
to perfectly match the mix to be paved. Specifications in terms
of surface accuracy and truth to line and level are similar to those
for road construction. The smoother the pavement, the less aircraft
shudder as they touch down.
The smoother the pavement,
the less aircraft shudder
The asphalt used on this project is a special mix. After
thorough testing, construction experts at Frankfurt/Main International
Airport decided for a high tech asphalt containing polymer modified
binder. The advantage of this mix is that it can be paved at relatively
low temperatures and immediately compacted by rolling. Temperature,
indeed, is one of the crucial aspects on this airport project, for
only little time is left for the pavement to cool. By 6 o’clock
in the morning pavement temperature is low enough to bear the weight
of landing aircraft. This, however, only works if weather permits.
Too high ambient temperatures would prevent the mix from cooling
in the short time available. As a result, paving operations are
suspended during the hot summer season, during icy winter nights
and also at times of heavy rainfall.
The asphalt is still steaming
as the first aircraft approach
This night, too, a tracked SUPER 1900 and a SUPER 2100
paver are ready for service on the high-security job site at Frankfurt/Main
International Airport. The pavers need to wait their turn. First,
excavators fitted with hammers start shattering the deformed asphalt
pavement with sections more than 30 years old of a runway which
so far had handled some 200,000 aircraft movements a year with each
aircraft weighing up to 300 tonnes. On compacted crushed stone and
sand, mix for the first layer of asphalt base, 24cm thick, is then
dumped, spread and compacted by dozers. Using a paver for this job
is not possible due to the necessity of embedding in this layer
supply piping, 22.5cm in diameter, for the light beacons alongside
the runway.
After that, the second layer
of asphalt base, also 24cm thick, is laid by the VÖGELE SUPER
1900 and SUPER 2100 pavers. They pave the asphalt mix at temperatures
between 125 and 135°C. The pave speed is 2m/min. A wax added
to the bitumen allows paving at this low temperatures. Conventional
mixes need paving at temperatures a good 50°C higher.
| |
| |
| A true challenge:
high-precision work, perfectly co-ordinated, by all machines
on the scene. |
When the first
aircraft will land in 2 hours‘ time, the pavement must
have cooled by 40°C. |
1,400 tonnes of asphalt paved
in 4.5 hours’ time
Next is a 12cm asphalt binder course, which together with
the base courses totals 60cm of special asphaltic mix. Asphalt paving
needs to be carried out in 4.5 hours’ time. The density produced
by the HPC screed in TP2 version is some 85% before 4 HAMM DV-8
rollers come in. Asphalt temperature still is 100°C. From that
point of time 90 minutes are left for cooling by another 15°C,
a temperature then low enough to allow landing with no risk neither
for aircraft nor for the pavement. By the way, the workers not only
pave 1,400 tonnes of special asphaltic mix for the new runway every
single night, they also remove an equal quantity of debris, install
light beacons for the runway and apply traffic line markings. In
the morning they hand back the runway to air traffic swept perfectly
clean.
Rehabilitation of the high tech runway,
however, is not yet completed. So far, the individual stretches
have been paved in a transverse direction. The top wearing course,
however, must run parallel to the direction of take-off and landing.
The reason: a pavement surface with transverse joints would cause
substantial vibrations to aircraft. Therefore, every seven weeks
the job site at Frankfurt/Main International Airport experiences
particularly busy nights. Excavators may now disappear from the
scene for five overnight closures. Instead, four WIRTGEN cold milling
machines take over and start milling off 4cm of the binder course
in 2m width.
Every seven weeks
mix is milled off again
They are followed by VÖGELE pavers. Four
of them now – the two regular SUPER 1900 and SUPER 2100 machines
plus the stand-by units lay wearing course in a longitudinal direction.
They replace the 4cm of binder milled off with 4cm of asphalt containing
polymer modified binder at a pave speed of 5m/min. Airport manager
Zintel is happy about everything going to plan and on schedule.
His relief is understandable, for the nights at Frankfurt are nerve-racking.
When an evening flight leaves the US and crosses the Atlantic, passengers
on board are not aware that the place on the area of Frankfurt/Main
International Airport where they are going to land is just being
shattered. At the time of their arrival, WIRTGEN cold milling machines,
VÖGELE pavers and HAMM rollers will have once again successfully
completed their floodlight job for that night. Rehabilitation of
the Northern runway is a very special project also for Dieter Schwenninger.
“This is the most impressive job site I have ever seen”,
he says. He has seen a lot of them, indeed.
Project
Details:
Client:
Project:
Duration:
Completion:
Contractor:
Equipment:
Materials:
Base Course:
Wearing Course:
Paving Operations: |
Frankfurt Airport AG
Rehabilitation of Northern Runway
12 months
Summer 2005
Kirchhoff-Heine Straßenbau GmbH & Co. KG, Langenargen
VÖGELE SUPER 1900 and SUPER 2100 Pavers
HAMM DV-8 Rollers, WIRTGEN W 2000 Cold Milling Machines
Low-temperature mix with SABOBIT wax additive
Pave Speed: 2m/min., Total Thickness Paved: 60cm
Asphalt containing polymer modified Pave Speed: 4m/min., Layer
Thickness: 4cm
Laydown Rate: 1,400 tonnes in 4.5 hours, 900m2 paved, Paving
Temperature: 125 – 135°C |
|